NEWS FLASH

Towanda, PA- PANDA ENERGY/ GEMMA POWER SYSTEMS
CCT COGEN GLOBAL- CONDENSOR CLEANING TECHNOLOGY

CCT COGEN GLOBAL just completed the Steamblowing of the HRSG and the Steam Turbine Generator/ ACC package in 32 hours, this 1X1 Configuration utilizes steam from a VOGT HRSG to feed steam to a Siemens STG and EVAPCO ACC. The process employed by CCT involves Hydrolazing of the ACC and steam piping, followed by atmosphere releasing of steam and gross debris to the CCT exhausters, then steamblowing through our temporary piping with our proprietary sparger to the ACC. CCT Then returns the flow back to our exhausters and target assembly in order to meet the Turbine manufacturer criteria for cleanliness. The targeting met the Siemens criteria for cleanliness and is typical for industry standard.